News

Sh170m projects stall due to bandit attacks, Nanok claims

Thursday, October 15th, 2020 00:00 | By
Turkana Governor Josephat Nanok when he appeared before Senate Committee. Photo/PD/SAMUEL KARIUKI

Hillary Mageka @hillarymageka

Development projects worth Sh170.54 million in Turkana have stalled due to continuous bandit attacks, Governor Josephat Nanok said yesterday.

Nanok told the Senate County Public Accounts and Investment Committee (CPAIC) that his administration failed to complete the projects in time because of the frequent attacks by armed militia.

In a moving explanation to the committee, the governor narrated how contractors have been forced to abandon sites because of  bandit attacks and vandalism of machinery and other forms of insecurity in the county.

“Many of our projects have stalled not because there is no budgetary allocation but because of the bandit attacks.

It is so serious Mr Chairman,” the Governor told the committee chaired by Kisii Senator Sam Ongeri.

Retired Auditor-General Edward Ouko in his audit report for the year ending June 2018, disclosed that 10 projects worth Sh170.54 million initiated by the county  had stalled.

This even as it emerged that the county government risks losing some Sh21.2 million should an appellate court rule in favour of a contractor, who allegedly failed to supply a firefighting equipment despite receiving full payment.

In his report, the Auditor held  that the county government irregularly paid Sh21.28 million for a firefighting truck.

Available information according to the Auditor, the amount for the purchase of the truck had not been budgeted for during the year under review.

 “In addition, procurement records such as requisitions, tender advertisements, evaluation, award committee minutes, inspection acceptable committee report were not availed for audit,” Ouko’s report reads in part. 

Entire amount

It adds: “Further, logbook for the firefighting truck was also  not provided for review. 

Consequently, the propriety of Sh21 million on the purchase of the truck could not be confirmed.”

In defence, Nanok told the committee that the fire fighting equipment was provided in 2015-16 Financial Year. 

In addition, the contract was awarded to M/s Winston International Ltd, who upon receiving a payment of Sh21, 280, 780 based on the bank guarantee from the Diamond Trust Bank Ltd.

“The contractor, however, failed to deliver the track as per the contract, which led the county government to go to court to sue the company,” the governor told the nine-member panel.

While the court ruled in the county’s favour to recover the money plus a 13 per cent interest, the county chief said, the firm appealed the ruling in a higher court.

The ruling, which if delivered in favour of the contractor could cause the taxpayer to lose the entire amount, is yet to be delivered.

“Suffice to say that, due to the rapid urbanisation and expansion of Lodwar Municipality, the county government initiated a process to procure another fire engine following the expiry of the contract by Winston International,” the governor held.

However, Senators took issue with governor’s responses demanding to know whether the county officers did due diligence before awarding the contract.

“Do your officers do due diligence? Because in most of the queries here, it is either contracts have been terminated or contractor has failed to deliver.

What is so hard for your officers to deal with these issues that appear chronic in Turkana?” Nandi Senator Samson Cherargei asked.

More on News


ADVERTISEMENT